Land Hitch Delays New Bangkok Skytrain Line
The Transport Ministry permanent secretary says the launch of the Red Line BTS train service from Bang Sue to Taling Chan is likely to be postponed after problems concerning land expropriation caused a significant delay in construction.
Transport Ministry Permanent Secretary Supoj Sublom disclosed that progress in the construction of the Red Line Skytrain, connecting Bang Sue with Taling Chan, is around 50 percent completed, which is about 20 percent less than scheduled.